0

Offshore Wind Installer - SHARING KNOWHOW IN OFFSHORE WIND CONSTRUCTION
Sharing knowhow in offshore wind construction

Going Local: The Evolution of A2SEA Mobilisations

a2sea_sea-installer_bkr1_small

By Jens Nielsen, Director, Head of Procurement, A2SEA

We have now finalised two locally based mobilisations in the UK, representing a clear forward step in bringing projects and jobs to the region. So what has it been like to do this for the first time? And does it mean for the future?

Continue reading

Offshore wind energy gets busy on the Humber

a2sea_andy-reay

By Andy Reay, A2SEA Regional Manager for the UK

The Humber may not be that long as rivers go (just 59 kilometres from one end to the other), but its lack of length isn’t about to stop it being one of the busiest spots in offshore wind energy next year. In fact, the area will be home to both operations & maintenance projects, as well as considerably more offshore construction, too.

Actually, the Humber isn’t a river at all. Situated on the east coast of northern England and flowing into the North Sea, it’s a tidal estuary formed where the River Trent and the River Ouse meet each other. In 2017, for the first time, A2SEA will be bringing two jack-up vessels to the area, kicking off two new projects that will see components being loaded out from Siemens’ new £160 million turbine blade manufacturing, project construction, assembly and service facility at Green Port Hull.

Continue reading

Success is: Being in the right spot at the right time

burbo-bank

By Klaus Holm Nissen, Project Manager, A2SEA

SEA INSTALLER and her crew have just installed the eighteenth of 32 MHI Vestas V164-8.0 MW turbines at Burbo Bank Extension. So far, we’ve made excellent progress, despite having to work with a lot of new, specialised lifting equipment for these large components. With the learning curves behind us, and if the weather continues to cooperate as nicely as it has to date, we expect to be finished mid to late December.

This is the first time we’ve installed a MHI Vestas V164-8.0 MW turbine. Yet the task presents relatively few challenges for us. Perhaps the most difficult part of the project, seen from A2SEA’s point of view, is the sea bed in the area. With a lot of clay and sand, as well as some silt, it’s a tricky task to jack up securely. That kind of surface composition can be very sticky, which initially had us thinking we might have problems retracting the legs. But it didn’t turn out to be much of a problem. There were, of course, some extended pre-load periods in order for us to compress the soil sufficiently and make sure it was able to support the vessel – even in a storm.

Continue reading

Turbine installation and the levelised cost of energy: Bigger vessel payloads

gode-wind-blade_owiblog

By Hans Peter Johannsen, Vice President, Projects.

This is the third article in our series about reducing the LCoE in the offshore wind industry through optimising turbine loading, transport and installation.

A2SEA’s internal data supports wider industry observations that the cost of turbine installation per installed MW is, in fact, coming down. From our perspective (and remembering that turbine installation is a minor part of an wind farm’s overall development), there are gains to be made whenever we can load more megawatts at a time onto our vessels. This ability is strongly assisted by the increasing amount of power generated by larger turbines such as the MHI Vestas 8 MW. But that’s far from the full story.

Continue reading

Work wise, think twice: Keeping our bodies safe

burbo-bank-ext_first-turbine_sea-installer_a2sea_dong-energy

By Kirsten Bank Christensen, Vice President, HSEQ at A2SEA A/S

Musculoskeletal injuries are an ever-present hazard in the offshore wind installation business. They’re defined as injuries that affect the human body’s movement or musculoskeletal system (muscles, tendons, ligaments, nerves, discs, blood vessels and so on). And, while many have an obvious and immediate cause, such as a back injury caused by lifting a heavy object on an awkward angle, others may be ‘occupational illnesses’ – damages that creep up on a worker over many years. In any case, this is a serious issue that can have permanent and devastating consequences at both professional and personal levels.

Continue reading

Tightening up the tendering process

dong_gow_wka_f_020_owi-blog

By Tony Millward, Vice President, Tender & Contracts, A2SEA

Tendering has been part of the offshore wind industry since its inception – and it’s crucial for arriving at an efficient and safe turbine installation plan. Yet still today, there are elements of the tender process that can be improved. So what makes for a good process?

For me, one of the most important aspects to tendering is simply this: Who’s at the table? At A2SEA, we always front with a full team comprising commercial, technical and legal advisors in all phases. This hasn’t been the norm on the other side of the table – but it may well be where things are headed in the future.

Continue reading

ENSURING SUPPLIER SAFETY VIA BEST PRACTICES (PART 2)

gode-wind_people_owi-blog

By Kirsten Bank Christensen, Vice President, HSEQ, A2SEA

Mobilisation projects are a valuable opportunity for cooperatively improving site safety together with many suppliers. This is the second of two posts describing how A2SEA’s ZERO HARM Mobilisation can lift supplier safety performance, and focusing on induction, HAZID/HAZOP workshops as well as results and learnings.

Continue reading

A2SEA shows off its Olympic teamwork

a2sea_jens-frederik-hansen_4

By Jens Frederik Hansen, CEO, A2SEA

An organisation that can work well together as a team is the pride and joy of any CEO. And A2SEA’s recent team-building day was certainly a day to remember. Not just because my own team won (that’s not the point of a team-building day, of course), but because the company’s Team Built spirit truly came to the fore.

Arranged at Vejlefjord, and surrounded by a beautiful park and the fjords themselves, as many of the company’s staff as could be gathered for the day were put through their paces at the A2SEA Olympic Games. It was a great day that had everyone involved, at times giving their utmost in athletic performance, at other times cheering their team members on. And I’m quite sure the company’s current “From Fredericia to Berlin” fitness drive, which has almost everyone walking the equivalent of 10,000 steps a day for 60 days, helped us all to look more like Olympic stars, too.

The organisation really got behind the event – and we were lucky with the weather, which is no easy feat in Denmark, if you’re familiar with a typical Danish summer!

First MHI Vestas 8MW turbine installed

burbo-bank-ext_first-turbine_sea-installer_a2sea_dong-energy_4_low-res

By Jens Frederik Hansen, CEO, A2SEA

On September 8, SEA INSTALLER successfully installed the first of the MHI Vestas V164-8 MW turbines – the largest offshore wind turbines ever sold for commercial operation – at the Burbo Bank Extension project. The project will add round 258 MW of capacity and stretches over 40 square kilometres.

Installing these turbines is nothing short of fantastic, and we are very pleased to work with MHI Vestas again. The preparation for the project was smooth and professional and the whole experience to date has been very positive. We look forward to installing more of these enormous turbines during the rest of this project and in others to come.

Read more about the project here.

Turbine Installation and the Levelised Cost of Energy: Taller and heavier

Post aug 2016_HP_Taller anmd heavier

By Hans Peter Johannsen, Vice President, Projects.

This is the second article in our series about reducing the LCoE in the offshore wind industry through optimising turbine loading, transport and installation.

These days, A2SEA is as busy as ever, working through a pipeline of turbine installation projects that shows no sign of slowing down. Such healthy demand is a blessing, of course, but we’re equally lucky in that the purpose-built vessels SEA CHALLENGER and SEA INSTALLER were initially designed to handle not just the installation of turbines, but foundations as well. Why is that so lucky? It’s all about how much they can handle.

Continue reading